CURRENT PROJECT
- House Extension -
Status: Ongoing
Works are currently underway on a residential house extension at Cranston Road. The project has progressed through the initial demolition and groundwork stages, with excavation and drainage preparation completed in accordance with approved designs. Concrete foundation works have now been successfully completed, including 600mm wide strip foundations, ground beams, and pad foundations, all constructed in line with the Structural Engineer’s drawings and calculations.
Foundation depths were formed to meet structural and Building Control requirements, with finished floor levels carefully set to achieve a level threshold between the internal floor and the external garden paving. These completed works provide a compliant and structurally sound base for the next phase of construction as the project continues to progress.
Joy Design and Build
〰️
Joy Design and Build 〰️
DEMOLITION STAGE
This phase involved the careful demolition and removal of existing external groundworks and structures to prepare the site for new construction. Works included breaking out concrete and hardstanding areas, excavation of contaminated and unsuitable ground, and segregation of demolition waste such as concrete, soil, timber, and mixed materials. All debris was stockpiled for controlled removal and disposal, ensuring the site was left clear, levelled, and ready for the next stage of construction.
Joy Design and Build
〰️
Joy Design and Build 〰️
EXCAVATION STAGE
This stage involved the excavation of trenches to accommodate new drainage runs in accordance with the approved layout. Works included careful hand and mechanical excavation to the required depths, exposing existing drainage where necessary and allowing for inspection and connection. Temporary support and safe access were maintained throughout the works.
Excavated material was removed or stockpiled as required, and trenches were prepared to receive new drainage pipes, ensuring correct line, level, and falls. All works were carried out with consideration to existing structures and services, leaving the site ready for installation and backfilling in the next phase.
Joy Design and Build
〰️
Joy Design and Build 〰️
CONCRETING STAGE
Concrete was placed within the prepared trenches to form a level and stable base for the new drainage installation in accordance with the approved drawings. The concrete was leveled to the required line and fall to ensure proper support and drainage performance. All works were carried out with care to protect existing structures, and the concrete was left to cure before proceeding to the next construction stage.
Joy Design and Build
〰️
Joy Design and Build 〰️
PIPING INSTALLATION
This stage involved the excavation and preparation of trenches to install new underground drainage runs in accordance with the approved drawings. Works included careful hand and mechanical excavation to the required depths, exposing existing drainage connections where necessary and ensuring all levels and falls were accurately set.
New pipework and fittings were installed, including inspection chambers and connections to existing systems. All drainage runs were aligned, levelled, and tested prior to backfilling. Excavated materials were removed or stockpiled as required, and safe access was maintained throughout. The site was left prepared for the next phase of construction.
Joy Design and Build
〰️
Joy Design and Build 〰️
WALL CONSTRUCTION STAGE
This stage involved the construction of the extension’s external and internal walls in accordance with the approved drawings and building regulations. Blockwork and brickwork were laid to the specified bond pattern, ensuring correct alignment, level, and structural integrity throughout.
Cavity wall construction was completed with the installation of damp proof course (DPC), cavity trays, and specified insulation to prevent moisture ingress and improve thermal performance. Wall ties were installed at the required spacings to securely connect inner and outer leaves.
All works were carried out with careful consideration to the proximity of neighbouring structures, maintaining required clearances and ensuring a high standard of workmanship in tight access areas. The walls were built up to the required heights, leaving the structure prepared for the next phase of construction.
Joy Design and Build
〰️
Joy Design and Build 〰️
FLOOR BASE & JOIST INSTALLATION
Concrete base works were completed to form a strong, level, and stable foundation for the new floor structure, in accordance with approved drawings and building regulations. Careful preparation and finishing ensured correct alignment, load distribution, and long-term durability.
Timber joists were then installed to create the floating floor section, set out at specified centres to provide structural support and stability. Integrated steel supports were incorporated where required to enhance strength, improve load-bearing capacity, and ensure overall structural integrity.
All works were carried out with attention to precision, safety, and workmanship standards. This stage marks a significant milestone in the build, establishing a solid and reliable framework ready for the next phase of construction.
Joy Design and Build
〰️
Joy Design and Build 〰️
ROOF STRUCTURE INSTALLATION
Roof structure works have now been completed to form a strong, secure, and weather-resistant framework, in accordance with approved drawings and building regulations. The roof has been carefully set out and constructed to ensure correct alignment, load distribution, and long-term structural performance.
Timber roof elements were installed with precision, forming the main structural framework and providing full support for the roof covering. All components were fixed and secured in line with structural requirements, ensuring stability and durability across the entire structure.
Where required, additional structural supports and fixings were incorporated to enhance strength and ensure compliance with load-bearing specifications. All works were carried out with close attention to detail, ensuring the roof structure is prepared for the next stages, including insulation and final roof finishes.
This stage marks a key milestone in the build, progressing the project towards full enclosure and readiness for internal works.
Joy Design and Build
〰️
Joy Design and Build 〰️
FLOOR INSTALLATION COMPLETION
Floor installation works have now been completed to form a stable, level, and secure surface, in accordance with approved drawings and construction standards. The flooring panels have been carefully laid and fixed to ensure correct alignment, load distribution, and long-term durability.
All elements have been installed with precision, creating a solid working platform for the progression of internal works. This stage provides improved site safety and allows for the efficient continuation of upcoming activities, including internal finishes and service installations.
The works were carried out with a strong focus on quality, accuracy, and workmanship. This milestone represents steady progress on site, bringing the project closer to the next phase of development and overall completion.
Joy Design and Build
〰️
Joy Design and Build 〰️
INTERNAL FINISHING & DOOR INSTALLATION
Internal works this week focused on painting and surface finishing, enhancing wall quality and preparing all areas for final detailing, in line with project specifications and finishing standards. Careful attention was given to surface preparation and application to achieve a clean, consistent, and high-quality finish throughout.
As part of the continued progress, French doors were successfully installed, improving both natural light and accessibility within the space. The installation was carried out with precision to ensure proper alignment, secure fitting, and smooth operation.
These works contribute to both the visual and functional development of the project, marking a key step towards completion. The space is now well-prepared for the final stages of finishing and detailing.